Plan Implementation

Pell Harbor waterfront trail grant

The Village of Pell Harbor (population 7,400) has won a competitive federal grant of $2,400,000 to build a 2.1-mile waterfront trail and boardwalk. The grant agreement requires a local match of $600,000, pays costs only on a reimbursement basis after documented expenses are submitted, and sets a three-year period of performance. The village has an annual general fund budget of about $11 million and an unrestricted reserve of $900,000.

The village planner is the grant manager, supported by a part-time finance clerk. A nonprofit land trust will carry out the habitat restoration as a subrecipient. During the application, an engineering firm volunteered to draft the project's statement of work and cost estimate, which the village intends to use in its request for proposals for design services.

Project budget
Budget lineAmount
Design and engineering$360,000
Construction$2,190,000
Habitat restoration (land trust subaward)$300,000
Grant administration$150,000
Total$3,000,000

Given the grant's payment terms, which step is MOST important before construction begins?