CAPM Practice Questions (2026) — Free Sample Questions with Answers

16 free CAPM questions from our 150-question bank, grouped by content domain. Each answer explains why the right option is right — and why every wrong option is wrong.

0 of 16 answered — answer a question to check it Take a full CAPM practice test

Project Management Fundamentals and Core Concepts

Question 1

A project manager reviews this meeting record to find out why the weekly design review is not working. Which change would most directly improve the meeting?

Weekly design review: meeting record
ItemRecord
Attendees6, including the design lead who approves designs
AgendaNone circulated; topics raised from the floor
TimeScheduled 60 minutes; ran 95 minutes
DiscussionMoved among five topics; design approval deferred for the third week
Action itemsFour, each with an owner and a due date
Show answer & explanation

Answer: C

Extend the meeting to 90 minutes: More time without structure tends to produce more drift, not decisions.

Invite the sponsor to every weekly meeting: The design lead who approves designs already attends, so the decision-maker is present.

Send an agenda with objectives beforehand: Correct. With no agenda or stated objectives, the meeting drifts across topics, overruns and fails to reach the approval decision. An agenda sent in advance, with the decision listed as an objective, gives focus and lets people prepare.

Assign owners to the action items: The record shows that every action item already has an owner and a due date.

To evaluate a meeting, check for an agenda with objectives, the right attendees, time control and clear outcomes; fix the element that is missing.

Question 2

A project manager is reviewing this RACI chart for a new reporting tool before sharing it with the team. Click the activity row that contains a role-assignment conflict.

Click the correct area of the figure.

RACI chart: reporting tool project
ActivitySponsorPMBADeveloperGather requirementsCARCApprove requirementsARCIDesign solutionIARABuild solutionIACR
R = responsible, A = accountable, C = consulted, I = informed
Show answer & explanation

Answer: C

First activity row: The first row has one accountable person (PM) and a responsible doer (BA), which is valid.

Second activity row: The second row has one accountable person (sponsor) and a responsible PM, which is valid.

Third activity row: Correct. "Design solution" shows A for both the PM and the developer. A RACI chart should name exactly one accountable person per activity, so two A's create unclear ownership and possible conflict over who makes the final call.

Fourth activity row: The fourth row has one accountable person (PM) and a responsible developer, which is valid.

In a RACI chart each activity has exactly one accountable (A) person, and at least one responsible (R) person does the work.

Question 3

A project manager notices that an engineer who usually speaks up in meetings has gone quiet, avoids eye contact and leaves as soon as meetings end. She senses that something is wrong and arranges a private chat. Which emotional intelligence competency let her pick up on this?

Show answer & explanation

Answer: D

Self-awareness: Self-awareness is recognizing one's own emotions and their effect; the PM is reading someone else's emotions.

Self-management: Self-management is controlling one's own emotions and reactions; nothing here is about the PM's own feelings.

Motivation: Motivation is the inner drive to pursue goals; it does not explain noticing another person's mood.

Social awareness: Correct. Social awareness (including empathy) is the ability to read and understand other people's emotions from cues such as body language and changes in behavior, which is what the PM did.

Self-awareness and self-management concern your own emotions; social awareness is reading other people's emotions; social skills use that awareness to manage relationships.

Question 4

A project manager is building a library extension and classifying stakeholders from the stakeholder register. The city's chief building inspector can halt all work with a stop order but has shown little interest in the project beyond permit compliance. Click the quadrant where the inspector belongs.

Click the correct area of the figure.

Stakeholder power/interest grid
HighLowPowerLowHighInterest
Vertical axis: power (low to high). Horizontal axis: interest (low to high).
Show answer & explanation

Answer: A

Upper-left quadrant: Correct. High power and low interest place the inspector in the upper-left quadrant. The usual strategy there is to keep the stakeholder satisfied: meet permit requirements and avoid surprises, without overloading them with detail.

Upper-right quadrant: Upper right is high power and high interest (manage closely); the inspector shows little interest in the project.

Lower-left quadrant: Lower left is low power and low interest (monitor); a stop order is real power over the project.

Lower-right quadrant: Lower right is low power and high interest (keep informed); the inspector has high power and low interest.

A power/interest grid turns stakeholder register data into engagement strategies: manage closely, keep satisfied, keep informed or monitor.

Question 5

The risk register lists "lead developer may leave" with a planned response: bring in a contractor already on standby. Today the lead developer resigns. What should the project manager do?

Show answer & explanation

Answer: A

Have the risk owner bring in the contractor: Correct. The risk has occurred, so the risk owner carries out the response already agreed in the risk register: bringing in the standby contractor. The PM then logs the event as an issue and updates the register with the outcome.

Hold a workshop to identify new responses: A response is already planned; redoing the analysis delays action that was prepared for exactly this event.

Add the resignation to the risk register as a new risk: The event is no longer uncertain, and the risk is already in the register; it is now an issue to act on.

Ask the sponsor to approve a new contingency budget: Escalation is not needed when the agreed response can be carried out within the plan.

When a registered risk occurs, carry out its planned response through its owner, record the issue, and update the risk register.

Question 6

A project manager reviews this draft scope statement before the scope baseline is set. Which part should be revised first?

Project scope statement (excerpt)

Product scope description: An iOS and Android app that lets clinic patients book, reschedule and cancel appointments.

Acceptance criteria: Patients are satisfied with the app.

Project exclusions: A web version; integration with the payroll system.

Constraints: Go-live by 30 June; budget of $250,000.

Show answer & explanation

Answer: D

Product scope description: The description names the platforms and the three functions, which is specific enough at this level.

Project exclusions: The exclusions clearly state what is out of scope, which helps prevent scope creep.

Constraints: The constraints give a firm date and a firm budget, so they are already specific.

Acceptance criteria: Correct. Acceptance criteria must be specific and measurable so that deliverables can be formally accepted. "Patients are satisfied" gives no test, metric or threshold, so the customer and team could not agree on when the app is accepted.

When critiquing scope, check that every acceptance criterion is measurable; vague terms such as "satisfied" or "user-friendly" cannot be verified.

Predictive, Plan-Based Methodologies

Question 7

At a monthly status review, a predictive project shows planned value (PV) of $100,000, earned value (EV) of $80,000 and actual cost (AC) of $64,000. Which conclusion about the project is correct?

Show answer & explanation

Answer: A

  1. Formulas: SPI = EV ÷ PV; CPI = EV ÷ AC.
  2. Substitute: SPI = 80,000 ÷ 100,000; CPI = 80,000 ÷ 64,000.
  3. Result: SPI = 0.80; CPI = 1.25.
  4. Interpretation: SPI below 1 means behind schedule; CPI above 1 means under budget for the work completed.

Behind schedule and under budget: Correct. SPI = EV ÷ PV = 80,000 ÷ 100,000 = 0.80, so the project is behind schedule. CPI = EV ÷ AC = 80,000 ÷ 64,000 = 1.25, so the work done has cost less than planned.

Ahead of schedule and over budget: This inverts both ratios (PV ÷ EV and AC ÷ EV); EV goes on top in SPI and CPI.

Behind schedule and over budget: SPI is below 1, but CPI is 1.25, above 1, which means under budget for the work performed.

On schedule and under budget: Spending less than PV does not mean on schedule; SPI of 0.80 shows only 80 percent of the planned work is done.

An index below 1 is unfavorable and above 1 is favorable; schedule and cost performance can move in opposite directions.

Question 8

A project manager performs forward and backward passes on the network shown. What is the total float of activity D?

Activity list for a lab-relocation project
ActivityPredecessorDuration (days)
A—4
BA8
CA2
DC3
EB, D5
All dependencies are finish-to-start with no lags.
Show answer & explanation

Answer: B

  1. Forward pass: A 0–4; B 4–12; C 4–6; D 6–9; E starts at the later of 12 and 9, so E runs 12–17.
  2. Backward pass: E LF 17, LS 12; D LF 12, LS 12 − 3 = 9; B LF 12, LS 4.
  3. Formula and substitution: total float of D = LS − ES = 9 − 6.
  4. Result: 3 days. Interpretation: D can slip 3 days without delaying the 17-day project finish.

0 days: Zero float applies to critical activities (A, B, E); D is on the shorter path A–C–D–E.

3 days: Correct. D has early start 6 and early finish 9. Working back from the 17-day finish, E must start by day 12, so D's late finish is 12 and its late start 9. Total float = LS − ES = 9 − 6 = 3 days.

6 days: 6 is D's early start, not its float.

9 days: 9 is D's early finish (and its late start); float is the difference between late and early start.

Total float = LS − ES (or LF − EF); activities on the critical path have zero float, while those on shorter paths have float.

Question 9

A project manager is reviewing the network diagram for a predictive equipment-installation project. Click the activity on the critical path that has the longest duration.

Click the correct area of the figure.

Activity-on-node network diagram
StartEndActivity A4 daysActivity D7 daysActivity B6 daysActivity C3 daysActivity E3 days
All dependencies are finish-to-start with no lags. Durations are in working days. Figure not drawn to scale.
Show answer & explanation

Answer: B

  1. List every path from Start to End: A–B–E, A–C–E and D–E.
  2. Add durations: A–B–E = 4 + 6 + 3 = 13; A–C–E = 4 + 3 + 3 = 10; D–E = 7 + 3 = 10.
  3. Result: the critical path is A–B–E (13 days); its activities are A (4), B (6) and E (3).
  4. Interpretation: B is the longest critical activity; D is longer but sits on a path with 3 days of float.

Upper-left activity: Activity A (4 days) is on the critical path A–B–E, but it is shorter than activity B.

Top-center activity: Correct. The paths are A–B–E = 4 + 6 + 3 = 13 days, A–C–E = 4 + 3 + 3 = 10 days and D–E = 7 + 3 = 10 days. The longest path, A–B–E, is critical, and B (6 days) is its longest activity.

Middle-center activity: Activity C lies on path A–C–E (10 days), which has 3 days of float, so it is not critical.

Lower-left activity: Activity D is the longest activity in the network (7 days), but its path D–E totals only 10 days, so it has 3 days of float and is not critical.

Right-hand activity: Activity E (3 days) is on the critical path, but it is shorter than activity B.

The critical path is the longest path through the network; the single longest activity is not necessarily on it.

Agile Frameworks/Methodologies

Question 10

What should the team facilitator do next?

Comic strip

Panel 1 — Team facilitator: "Let's look back at this iteration. What helped us, and what got in the way?"

Panel 2 — Developer 1: "The nightly build broke three times, and each time we lost most of a day."

Panel 3 — Tester: "Most stories reached me in the last two days, so testing was a rush."

Panel 4 — Developer 2: "I'd rather we try something different next iteration than just complain again."

Show answer & explanation

Answer: A

Help the team choose improvements to try: Correct. The retrospective exists so the team inspects its own process and commits to a small number of concrete improvements for the next iteration. The facilitator guides the team to decide; it does not decide for them (Agile Task 4).

Assign the build fix to the senior developer: Directing the solution undercuts self-organization; a servant leader helps the team choose its own actions.

Move the discussion to the iteration review: The iteration review is for inspecting the product with stakeholders, not the team's process.

Send a summary of complaints to the sponsor: Escalating turns a team-improvement event into reporting; the team owns and fixes its own process.

Retrospective = the team improves how it works and leaves with actionable improvements; review = stakeholders inspect the product.

Question 11

The release plan assumed the team would burn 20 story points per iteration. Click the iteration in which the team fell furthest behind the planned pace.

Click the correct area of the figure.

Release burndown: story points remaining
100500Points left1008076543401234Iterations completed
Solid line = actual points remaining at the end of each iteration. Dashed line = planned pace of 20 points per iteration.
Show answer & explanation

Answer: B

Segment from 0 to 1: Remaining work fell from 100 to 80, so 20 points were burned, exactly the planned pace.

Segment from 1 to 2: Correct. Remaining work fell only from 80 to 76, so the team burned 4 points against a plan of 20, a shortfall of 16. A flattening burndown line shows an iteration where little work was finished (Agile Task 3).

Segment from 2 to 3: Remaining work fell from 76 to 54, so 22 points were burned, slightly ahead of the planned pace for that iteration.

Segment from 3 to 4: Remaining work fell from 54 to 34, so 20 points were burned, the planned pace (the team is still behind overall because of the earlier stall).

On a burndown, the drop between two points is the work finished in that iteration; a nearly flat segment is where the team fell behind.

Question 12

An agile team completed 22, 18 and 20 story points in its last three iterations. The release backlog still holds 120 story points, and the team expects to keep the same pace. About how many more iterations will the release need?

Show answer & explanation

Answer: C

  1. Average velocity = (22 + 18 + 20) / 3 = 60 / 3 = 20 points per iteration.
  2. Iterations needed = remaining points / average velocity = 120 / 20.
  3. Result = 6 iterations.
  4. Interpretation: using the average (not the best or worst iteration) gives a realistic forecast of 6 more iterations.

2: This divides 120 by the 60-point total of three iterations, which is not a per-iteration rate.

5: This uses only the best iteration (120 / 22 ≈ 5.5) and rounds down, which is optimistic.

6: Correct. Average velocity is (22 + 18 + 20) / 3 = 20 points; 120 / 20 = 6 iterations. Velocity-based forecasting uses the team's average pace (Agile Task 2).

7: This uses only the slowest iteration (120 / 18 ≈ 6.7) and rounds up, which is pessimistic.

Forecast iterations = remaining backlog ÷ average velocity; use the average of recent iterations, not a single high or low one.

Business Analysis Frameworks

Question 13

At a product demonstration, the business analyst confirms that a new invoice-approval feature passes every acceptance criterion. The finance stakeholders say it still does not cut approval time, which was the reason for the project. What does this situation most likely indicate?

Show answer & explanation

Answer: D

A coding defect in the feature: A coding defect would show up as failed acceptance tests, but every criterion passed.

A team velocity that is too low: Velocity measures how much work a team completes per iteration; it says nothing about whether the result meets the business need.

Scope creep introduced by the team: Scope creep is unapproved added work; the problem here is that the intended outcome was not achieved.

Acceptance criteria that missed the real need: Correct. Validation confirms that requirements, and the solution built from them, meet the business need. A feature can pass every test and still fail the business objective if its acceptance criteria were never tied to that need, here, faster approvals (BA Task 6).

Passing acceptance criteria shows the product was built as specified; validation also asks whether it delivers the business value it was meant to.

Question 14

The product manager for a coffee chain's mobile app is adding a new feature, "Pay with gift-card balance." It cannot work until the gift-card balance engine is live, and marketing needs it available before the holiday campaign that starts in October. Click the release where the new feature belongs.

Click the correct area of the figure.

Coffee chain mobile app — product roadmap
Release 1MarchOnline orderingCard paymentsRelease 2JuneLoyaltyaccountsPoints earningRelease 3SeptemberGift-card balanceengineOrder historyRelease 4DecemberSales analyticsStaffschedulingTime
Four planned releases, left to right: March, June, September and December, with the features planned for each.
Show answer & explanation

Answer: C

Leftmost column: Release 1 (March) comes before the gift-card balance engine exists, so the feature could not work yet.

Second column from left: Release 2 (June) is still before the gift-card balance engine arrives in release 3, so the dependency is not met.

Third column from left: Correct. Release 3 (September) is the first release that contains the gift-card balance engine the feature depends on, and it ships before the October campaign. It is the only release that satisfies both the dependency and the deadline (BA Task 4).

Rightmost column: Release 4 (December) meets the dependency but arrives after the October campaign starts, so it misses the business deadline.

Place a component in the earliest release that both contains everything it depends on and meets the business date it must support.

Question 15

Which change would most improve this elicitation interview?

Comic strip

Panel 1 — Business analyst (to warehouse supervisor): "Thanks for meeting with me. I'm here to learn how returns are handled today."

Panel 2 — Business analyst: "You'd agree that a barcode scanner app would fix the delays, right?"

Panel 3 — Warehouse supervisor (shrugging): "I suppose so, if you think it would."

Panel 4 — Business analyst (writing in a notebook): "Great. Scanner app confirmed as the requirement."

Show answer & explanation

Answer: B

Invite the supervisor's manager to the interview: Adding a manager may make the supervisor even less willing to speak freely; the problem is the question style.

Ask open-ended questions about the current process: Correct. The BA asked a leading question that assumed the solution, and the supervisor simply agreed. Open-ended questions about how returns work today would draw out the real problems and needs before any solution is chosen (ECO BA Task 3, interviews).

Replace the interview with a survey: A survey suits many respondents; the issue here is leading questions, which a survey would not fix.

Demonstrate a scanner app prototype first: Showing a prototype first would anchor the discussion on the same assumed solution.

In interviews, ask open-ended, neutral questions about current work and needs; leading questions put the BA's solution in the stakeholder's mouth.

Question 16

A business analyst finds that the purchase-order approval workflow has three redundant sign-offs and proposes removing one. The accounts payable supervisor runs the workflow each day, but the finance director is accountable for how the process is designed and how well it performs, and must approve any change to it. Which stakeholder role does the finance director hold?

Show answer & explanation

Answer: C

Process manager: The process manager oversees day-to-day execution of the process; that describes the accounts payable supervisor, not the director.

Product owner: A product owner owns and orders an agile team's product backlog; it is not a role over a business process.

Process owner: Correct. The process owner is accountable for the design and performance of a business process and has the authority to approve changes to it, which is exactly the finance director's position here (ECO BA Task 1, stakeholder roles).

Project sponsor: The sponsor funds and champions a project; accountability for an ongoing business process belongs to its process owner.

The process owner is accountable for how a process is designed and performs and approves changes to it; the process manager runs it day to day.

Test yourself under exam conditions

Take the free CAPM test and get a score report by domain.

The full CAPM question bank is coming. Get an email when it launches.