Question 1 of 10

Predictive, Plan-Based Methodologies

A project manager is preparing a cost report for a predictive project from the earned value data shown. Which work package has the largest cost overrun?

Earned value data by work package ($ thousands)
Work packagePVEVAC
WP1323028
WP2202227
WP3181516
WP4454041