CAPM Practice Test 2

10 free CAPM practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

CAPM Practice Test 2Tutor mode

Question 1 of 10

Project Management Fundamentals and Core Concepts

While estimating, a team plans on a vendor delivering laptops within 30 days of the order. Nobody has confirmed this lead time with the vendor yet. Where should the project manager record it?