Question 1 of 10
Project Management Fundamentals and Core Concepts
A project manager is building a library extension and classifying stakeholders from the stakeholder register. The city's chief building inspector can halt all work with a stop order but has shown little interest in the project beyond permit compliance. Click the quadrant where the inspector belongs.
Click the correct area of the figure.
Stakeholder power/interest grid
Vertical axis: power (low to high). Horizontal axis: interest (low to high).