Question 1 of 10
Plan, Manage, and Execute Detailed Schedules
A capacity planner is checking week 14 at work center 50. Based on the orders below, what is the total load from all released and planned orders?
Orders scheduled at work center 50 in week 14| Order | Quantity | Setup (hours) | Run (hours per unit) | Status |
|---|
| A-1 | 100 | 2.0 | 0.10 | Released |
| B-2 | 250 | 1.5 | 0.06 | Planned |
| C-3 | 80 | 3.0 | 0.20 | Released |
| D-4 | 400 | 1.0 | 0.05 | Planned |