CPIM Practice Test 6

10 free CPIM practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

CPIM Practice Test 6Tutor mode

Question 1 of 10

Manage Quality, Continuous Improvement, and Technology

Use the following shift data for a filling machine: planned production time 480 minutes, unplanned downtime 60 minutes, ideal cycle time 0.5 minute per unit, 720 units produced, and 684 good units. What is the overall equipment effectiveness (OEE), to the nearest whole percent?