Question 1 of 10

Plan, Manage, and Execute Detailed Schedules

Last month a work center was available 400 hours. It actually worked 340 hours and produced 374 standard hours of output. Next week it will be available 80 hours. Using last month's utilization and efficiency, what is next week's rated capacity?