CQA Practice Test 14

10 free CQA practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

CQA Practice Test 14Tutor mode

Question 1 of 10

Audit Process

Audit File — CNC Machining Cell 3 (Internal Audit IA-26-07)

An aerospace parts manufacturer audited its CNC machining cells against its ISO 9001-based QMS and work instruction WI-210 Rev D, First-Article Inspection. The lead auditor wrote the nonconformity report (NCR) below and presented it to the production manager at the closing meeting. The production manager submitted the CAPA response 21 days later. The lead auditor is responsible for reviewing the response and for follow-up. The internal audit procedure requires verification of effectiveness before an NCR is closed.

Which revision would most improve the statement of nonconformity in NCR-26-07-02?