Define Phase

The activity network diagram shows the tasks for installing a new filling line at a beverage plant. How many days can activity C slip without delaying the project?

Activity network (activity on node)
A3 daysB4 daysC2 daysD6 daysE3 daysF2 days
Arrows show precedence. A precedes B and C; B and C precede D; C precedes E; D and E precede F.