Question 1 of 10

Improve Phase

A router assembly line works one 8-hour shift with two 15-minute breaks (27,000 s available) and must ship 500 units per shift. If the work is rebalanced for continuous one-piece flow, what is the theoretical minimum number of operators?

Current station cycle times (one operator per station)
StationS1S2S3S4S5S6S7
Cycle time (s)34484068223228
Total work content = 272 s per unit.