Question 1 of 10

Construction Documentation and Administration

The protection plan must show the contractor's materials staging area. Staging must stay outside the tree protection zone and the stream buffer, must not occupy the building pad, and must be reachable from the existing drive without crossing a protected area. Select the location.

Click the correct area of the figure.

Site plan — construction staging
Property linePublic streetDriveProposed buildingExisting oak to remain;dashed circle = TPZStreamStream buffer lineN
TPZ = tree protection zone. Not to scale.