A contractor believes the planting and paving work for a streetscape project is substantially complete. Place the activities in order.
Put the options in order: use the arrows (or drag) to move each one.
- 1Landscape architect issues the certificate of substantial completion
- 2Owner makes final payment, including the remaining retainage
- 3Landscape architect inspects the work and completes the punch list
- 4Contractor notifies the landscape architect and submits its list of incomplete items
- 5Landscape architect conducts the final inspection
- 6Contractor completes the punch list and submits close-out documents