A LEED v5 BD+C project attempted 64 points, and all prerequisites were approved. In final review, credits worth 3 points and 4 points were denied. Which certification level does the project earn?
Show answer & explanation
Answer: B
- 1. Start with the points attempted: 64 points.
- 2. Subtract the denied credits: 64 − 3 − 4 = 57 points awarded.
- 3. Compare with the levels: Certified 40–49, Silver 50–59, Gold 60–79, Platinum 80+.
- 4. 57 points falls in 50–59, so the project is LEED Silver.
Certified: Certified covers 40–49 points; the project keeps 57 points.
Silver: Correct. 64 − 3 − 4 = 57 awarded points, which falls within the Silver range of 50–59 points.
Gold: Gold (60–79) would apply to the 64 points attempted, but the level is based on the points awarded after review.
Platinum: Platinum starts at 80 points, far above this total.
The level is set by points awarded after review: Certified 40–49, Silver 50–59, Gold 60–79, Platinum 80+.