NASCLA Practice Test 1

10 free NASCLA practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

NASCLA Practice Test 1Tutor mode

Question 1 of 10

Procurement and Contracting Requirements

An owner wants to bid a utility project competitively, but the amount of rock excavation and unsuitable-soil removal can only be estimated before work begins. The owner wants to pay only for the quantities actually installed. Which contract type best fits?