Question 1 of 10
General Requirements
Based on the submittal log, which item may the general contractor release to its supplier for ordering now?
Submittal log (excerpt), returned by the architect| Submittal no. | Description | Submitted | Returned | Architect action |
|---|
| 03 30 00-01 | Concrete mix designs | Mar 3 | Mar 14 | Revise and resubmit |
| 05 12 00-01 | Structural steel shop drawings | Mar 5 | Mar 19 | Rejected |
| 08 11 13-01 | Hollow metal frames | Mar 10 | — | Under review |
| 09 29 00-01 | Gypsum board product data | Mar 11 | Mar 20 | Approved as noted |
Specifications require an approved submittal before ordering or fabrication.