NASCLA Practice Test 4

10 free NASCLA practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

NASCLA Practice Test 4Tutor mode

Question 1 of 10

Procurement and Contracting Requirements

A contract assesses liquidated damages of $750 per calendar day for late substantial completion. Substantial completion was reached 18 days after the original contract date, and final completion 6 days after that. The owner had granted a 4-day time extension by change order. What liquidated damages may the owner assess?