Project scenario: branch library

A county library system is planning a new, single-story branch library (Group A-3) with a floor plate of 120 ft by 90 ft. The building is not sprinklered; its fire area and occupant load fall below the thresholds that would require sprinklers.

The schematic plan provides a 1,200 net sq ft community meeting room with tables and chairs in the northeast corner, a 2,500 net sq ft reading room, 5,000 gross sq ft of book stacks and a 600 gross sq ft staff workroom. Corridors and restrooms serve these spaces and are not assigned a separate occupant load. The designer is checking the schematic plan against the code excerpt before the client review, so any problem found now can be fixed before design development.

Code excerpt (IBC 2021 Chapter 10, paraphrased)
ProvisionValue
Occupant load factor: library reading rooms50 net sq ft per occupant
Occupant load factor: library stack areas100 gross sq ft per occupant
Occupant load factor: assembly, unconcentrated (tables and chairs)15 net sq ft per occupant
Occupant load factor: business areas150 gross sq ft per occupant
Space with one exit or exit access doorway (Groups A and B)Maximum 49 occupants
Egress door swingSide-hinged egress doors serving 50 or more occupants shall swing in the direction of egress travel
Egress capacity factor, components other than stairways0.2 in per occupant; 0.15 in only with sprinklers and an emergency voice/alarm system
Exit separation1/2 of the maximum overall diagonal; 1/3 where the building is sprinklered throughout
Dead-end corridor limit20 ft; 50 ft only in sprinklered Groups B, E, F, I-1, M, R-1, R-2, S and U
Schematic plan: branch library
Meeting room1,200 net sq ft120 ft90 ftExit 1Exit 218 ft20 ft14 ft30 ftStaffworkroomBook stacksBook stacksReading room
Shaded areas are 5 ft wide corridors. Corridor lengths are measured to each dead end. Figure not drawn to scale.

How many exit access doorways must the community meeting room have?