PMP Practice Test 10

10 free PMP practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

PMP Practice Test 10Tutor mode

Question 1 of 10

Process
Case study — item 1 of 5

Case study 3 — MetroLink trip-planning app (agile, Scrum)

You are the project manager, serving in a servant-leader role similar to a Scrum Master, for a regional transit agency's trip-planning app. A cross-functional Scrum team of seven developers works in two-week sprints (10 working days). The product owner, Lena, is the agency's digital services manager. The sponsor is the vice president of customer experience.

The current release goal is offline mode: riders should be able to see saved trips and service alerts when they lose signal in the underground stations. The sponsor recently told the agency's board that offline mode would launch at the end of Sprint 7. The agency's accessibility policy requires that every release meet WCAG 2.1 AA.

The team works from a shared product backlog that only Lena orders. Its working agreements say that new requests go to the product owner, that the team pulls work into a sprint during sprint planning, and that sprints are never extended. The team uses an AI coding assistant approved by the agency's IT security office, and it holds sprint reviews with a rider panel every two weeks. The developers have worked together for about six months, and their velocity has begun to stabilize.

In Sprint 5 planning, the team committed to 40 story points after the sponsor urged them to "stretch," even though recent velocity was lower. On day 4, the marketing director asked two developers directly to add a fare-cap banner to the sprint, and they agreed. The chart below shows the Sprint 5 burndown through day 7. The tables show the team's velocity history and the release backlog that remains after Sprint 5.

Sprint 5 burndown (through day 7 of 10)01020304001234567Sprint dayStory points remaining
Ideal remaining Actual remaining
Velocity history
SprintPoints committedPoints completed
13022
23026
33230
43028
540In progress
Release backlog remaining after Sprint 5 (ordered by the product owner)
IDBacklog itemStory points
B-31Offline cache of saved trips21
B-32Sync and conflict handling when signal returns13
B-33Screen-reader labels for offline banners5
B-34Fare-cap alert13
B-35Usage analytics for offline sessions8
B-36Dark mode8
B-37Spike: AI-generated trip suggestions16
Total84

The product owner asks how many more sprints after Sprint 5 the team will need to finish the remaining release backlog. Using the average velocity of the last three completed sprints, what is the best forecast?