PMP Practice Test 4

10 free PMP practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

PMP Practice Test 4Tutor mode

Question 1 of 10

Process

A product owner on an agile program uses weighted shortest job first (WSJF) to order four features. Cost of delay is the sum of user/business value, time criticality and risk reduction/opportunity enablement. Which feature should be scheduled first?

Feature scoring (relative points)
FeatureBusiness valueTime criticalityRisk reductionJob size
A1111
B8855
C138513
D3188