PMP Practice Test 6

10 free PMP practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

PMP Practice Test 6Tutor mode

Question 1 of 10

People
Case study — item 1 of 5

Case study 1 — Harbor Valley Medical Center: scheduling and patient portal rollout (hybrid)

You are the project manager at Harbor Valley Medical Center, a 320-bed community hospital. The chief operating officer (COO) sponsors a 14-month, $4.2 million project that replaces the hospital's spreadsheet-based nurse staffing process with a scheduling app and adds an online appointment-booking portal for patients. Both products must exchange data with the hospital's existing electronic health record (EHR).

Leadership approved a hybrid approach. An external EHR integration vendor builds the interfaces under a fixed-price contract with three acceptance milestones, and the hospital's IT infrastructure group must upgrade the servers that host the integration engine; hardware lead times are 10 weeks. An internal agile team of nine (developers, a UX designer and a tester) builds the scheduling app and the portal in two-week iterations. The product owner is the manager of patient access. The clinical informatics lead, a registered nurse, represents nursing workflows on the team.

Constraints: every production release must be approved by the hospital's change advisory board (CAB); go-live must happen before the winter respiratory-virus surge; all systems must comply with HIPAA privacy and security requirements; and the portal must meet WCAG 2.1 AA accessibility. The hospital's information security policy prohibits entering protected health information (PHI) into any tool that has not passed a security review and been covered by a business associate agreement.

The vendor's integration engineers work remotely and roll off when the fixed-price contract closes, six weeks before go-live. After that, the hospital's IT operations team will support the interfaces around the clock.

In iteration 3, you review the stakeholder engagement assessment below with the product owner.

Stakeholder engagement assessment (iteration 3)
StakeholderCurrent engagementDesired engagementNotes
COO (sponsor)LeadingLeadingChairs monthly steering meeting
Director of NursingResistantSupportiveMissed the last two iteration reviews
Privacy officerNeutralSupportiveApproves any new tool that touches PHI
Night-shift charge nursesUnawareSupportivePrimary users of shift swaps
Patient advisory councilUnawareNeutralVolunteers available monthly
EHR vendor account leadSupportiveSupportiveContract owner for the vendor
Engagement levels: Unaware, Resistant, Neutral, Supportive, Leading.

Shortly after this review, you learn that the Director of Nursing told her unit managers that the scheduling app "will only add clicks to an already long shift." She has not raised the concern with the project team. What should the project manager do first?