PMP Practice Test 8

10 free PMP practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

PMP Practice Test 8Tutor mode

Question 1 of 10

Process

On a predictive project, a seller under a fixed-price contract submits an invoice for extra configuration work. The seller says the work was outside the statement of work (SOW); your team believes it was included. What should you do first?