Midway through the year, senior management cuts the internal audit budget by 30%, leaving several high-risk engagements in the approved plan without staff. What should the CAE do first?
Show answer & explanation
Answer: A
Inform the board of the cut and its effect on coverage of high-risk areas: Correct. A budget cut that prevents the function from covering significant risks is a resource limitation that can impair independence. The CAE must communicate its impact to the board, which approves the plan and decides how to respond.
Reduce testing on every engagement so the full plan still fits the budget: Incorrect. Inadequate: thinning all work hides the impact and risks insufficient work on high-risk areas without the board's knowledge.
Revise the internal audit plan and begin executing the revised plan immediately: Incorrect. Authority reversed: significant changes to the plan need board review and approval before they take effect.
Accept the reduction as a decision that belongs to senior management alone: Incorrect. Inadequate: the budget affects the function's ability to fulfill its mandate, so the board must be informed rather than the cut accepted silently.
When resources fall short of what the plan needs, the CAE communicates the impact to the board before significant plan changes are made.