Question 1 of 10

Public (employee, patient, visitor) Safety in the Healthcare Facility

To reduce downtime, the radiology manager asks to extend PM intervals on a radiographic room beyond the manufacturer's recommendation under the hospital's alternate equipment management (AEM) program. Under CMS hospital requirements, what is the correct response?