PE Civil Practice Test 13

10 free PE Civil practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

PE Civil Practice Test 13Tutor mode

Question 1 of 10

Water Resources and Environmental

A utility is choosing between two pumps for a raw-water booster station. Pump A costs $120,000 installed and has an annual energy cost of $18,000. Pump B, a premium-efficiency unit, costs $165,000 installed and has an annual energy cost of $13,500. Both have a 20-year life, no salvage value, and equal maintenance costs. The utility uses an interest rate of 5% per year, for which (P/A, 5%, 20) = 12.4622. The present-worth advantage of the alternative with the lower present worth of costs over the other alternative is most nearly: