PE Civil Practice Test 15

10 free PE Civil practice questions in the real exam format, covering the official content areas, with an explanation for every answer.

PE Civil Practice Test 15Tutor mode

Question 1 of 10

Water Resources and Environmental

A state is setting a total phosphorus TMDL for a stream reach using the elements shown. The municipal wastewater treatment plant receives all of the remaining allocation. Use 1 cfs = 0.646 MGD. The effluent TP concentration limit for the plant at its design flow is most nearly:

Total phosphorus (TP) TMDL elements for the impaired reach
ElementValue
Design low flow at the downstream end of the reach40 cfs
Instream TP target0.10 mg/L
Margin of safety (explicit)10% of the loading capacity
Load allocation, nonpoint sources9.0 lb/day
Wasteload allocation, municipal separate storm sewer system (MS4)3.5 lb/day
Wasteload allocation, municipal WWTP (design flow 1.5 MGD)remainder