Question 1 of 10
Management and Leadership
Release-of-information system replacement project (durations in working days; invented data)| Task | Description | Duration | Predecessor(s) |
|---|
| A | Define requirements | 3 | — |
| B | Configure software | 5 | A |
| C | Develop staff training materials | 4 | A |
| D | Build and test interfaces | 6 | B |
| E | Train ROI staff | 2 | C |
| F | Go-live and stabilization | 4 | D, E |
The HIM director is leading the project in the table. What is the shortest time in which the project can be completed?