Question 1 of 10
Leadership
Project task table: scanning conversion of legacy paper records (invented data)| Task | Description | Duration (days) | Predecessor(s) |
|---|
| A | Inventory legacy paper records | 5 | None |
| B | Configure document types and indexing rules | 4 | A |
| C | Train scanning staff | 3 | A |
| D | Pilot scanning on one record series | 6 | B, C |
| E | Full conversion scanning | 10 | D |
| F | Notify clinicians of the go-live date | 2 | B |
Each task starts as soon as all of its predecessors finish. The project is complete when every task is finished.Using this project task table, what is the shortest possible duration of the project?